9/20/2026
Doug Carrick
Doug will be here next week to review the following;
- final cart path paving plans
- tree removal plans around #8 pond
- work completed on #6, #12 and #17 along with our remediation lists for the contractors.
The tree removal around the pond will begin in the coming weeks and be completed for opening day next spring.
Our plan is to install the windpump late this fall or early next spring in advance of opening day. The tree removal around the pond will expose several long views around the property and needs to be completed in advance on the #8 pond liner installation in 2028.
Project Update
I am just reconciling the final invoicing and returns with Rain Bird on the sprinkler parts. I’m expecting one more invoice from our irrigation consultant and that will wrap up everything except the fall remediation work, which will also begin after Thanksgiving weekend.
Both contractors are returning to address some deficiencies and at the completion of the remediation work the final two holdbacks will be released. Once the holdbacks are released, it will officially wrap up the financial component of the projects.
Everything remains on budget and I’ll provide a detailed breakdown for the entire project in the October 6
th Mad Post.
If you have any other questions, you can reach me by email at
[email protected] or by phone at 705-428-3673.
Thank you,
Gary Ward,